開關(guān)、插座安裝工程技術(shù)交底-建筑安裝.doc
進入下載頁
一、 施工準備
(一) 作業(yè)條件
1、 各種管路、盒子已經(jīng)敷設(shè)完畢,損壞的盒子已換掉。
2、 盒子縮進裝飾面超過20mm的已加套盒,且套盒與原盒有可靠的措施,拔插時不能將套盒與面板一起拔出。
3、 盒子縮進裝飾面不夠20mm已用高強度水泥砂漿外口抹平齊,內(nèi)口抹方正。
4、 線路的導(dǎo)線已穿完,并已對各支路完成絕緣搖測。
5、 墻面抹灰、油漆及壁紙等內(nèi)裝修工作均已完成。
為防止土建施工污染插座面板,水泥地面、鋪磚地面、水磨石、大理石地
First, construction preparation
(A) Operating conditions
1, various pipes, boxes have been completed the laying of the damaged box has been replaced.
2, box decorative surface indentation that has added more than 20mm Packing carton, and Packing carton with the original box with reliable measures, plug Packing carton with the panel, was unable to pull together.
3, box decorative surface indentation 20mm has enough high-strength cement mortar smoothing Qi of foreign population, which I wipe Founder.
4, the line had been wearing complete wire and insulation has been completed on each branch shake test.
5, wall plaster, paint and wallpaper and other interior decoration work had been completed.
To prevent pollution of socket panel civil construction, cement floors, tiling floors, terrazzo, marble