第一章 施工組織方案
1.1 施工測量
本工程施工測量的主要任務(wù)是:施工控制網(wǎng)的建立(包括全線主控制網(wǎng)的復(fù)測與施工控制網(wǎng)點(diǎn)的加密),施工細(xì)部結(jié)構(gòu)以及形體的幾何尺寸,傾角、線型等精密定位,本工程涉及到工程測量與安裝測量兩方面的技術(shù)問題,測量技術(shù)含量高,施工測量精度要求高,因此我項(xiàng)目部將本工程施工測量列為首要工序,重點(diǎn)管理,要求測量部門技術(shù)超前,科學(xué)管理,及時(shí)總結(jié),精益求精,以高質(zhì)量、高效率地完成本工程施工測量任務(wù)。
1.1.1測量質(zhì)量技術(shù)管理
(1)測量硬件設(shè)施配置:本工程中,將投入1臺(tái)高精度的全站儀,2臺(tái)高精度的精密水準(zhǔn)儀,2臺(tái)J2經(jīng)緯儀以及相關(guān)測量設(shè)備。
(2)測量人員配備:在本工程中我單位將調(diào)派富有市政道路施工測量經(jīng)驗(yàn)的測量工程師1名和測量工2名。
(3)測量技術(shù)管理:在本工程施工中擬建嚴(yán)格的測量校核、復(fù)核、審核技術(shù)管理制度,除在測量部門內(nèi)部實(shí)行此制度進(jìn)行自檢外,項(xiàng)目部實(shí)行項(xiàng)目總工程師、專職質(zhì)檢員、測量技術(shù)主管三級參加的技術(shù)復(fù)核制度,單項(xiàng)技術(shù)干部參加并負(fù)責(zé)單項(xiàng)的測量技術(shù)復(fù)核工作,本工程測量技術(shù)管理流程見下圖。
Chapter Organization Plan
1.1 Construction Survey
Construction Survey of the main tasks are: Construction Control Network (including the full range of master control network and construction of complex test control network encryption), construction detail structure and shape of the geometric dimensions, angle, line, such as precision positioning, the project Surveying involves measuring and installation of two technical problems, high levels of measurement, construction measurement of high precision, so I project the Department will measure the construction process as a primary focus on management, ahead of required measurement sector technology, scientific management, timely summary of excellence, with high quality, high efficiency measurement tasks in this construction.
1.1.1 Measurement Quality and Technology Management
(1) measurement hardware configuration: this project will be put into a high precision of the total station, 2 sets of high accuracy, precision leveling, 2 J2 theodolite and related measuring equipment.
(2) measuring staffing: In this project I units will be deployed to the rich experience of the municipal road construction survey measurement and measurement engineers a working 2.
(3) Measurement and Management: In this strict construction of the proposed measurement check, review, audit technology management system, in addition to measuring the implementation of this system within the department to conduct self-inspection, the project chief engineer of the Ministry to implement the project, full-time quality control member of measurement technology to participate in the technical review of tertiary charge system, participation and individual technical cadres responsible for reviewing the work of individual measurement techniques, the project management process measurement shown below.